Below, drains
are keyed out for extra thick material at these critical edges
Below, joints and large cracks are keyed out also to bridge these
areas with extra floor material
Below, floors are Shot Blasted to rock for permanent bonding profile
Below, an aggressive blast to heavy rock will ensure a permanent
floor coating bond
Below, 45 Degree solid cove is applied to provide effective sanitation
Below, a slurry of resin and sand is applied to fill in voids and
provide a thick layer base coat
Below, 3 layers have been applied and are ready for top coat resulting
in 1/4 inch total thickness
Below, top coat is applied with non skid to provide a safe durable
surface
Below, finished floor surface is ready to use next day for heavy
traffic and years of durablility